In Association with Acres of Canada, we carried out a Pre-Feasibility & Feasibility study, preliminary & detailed designs, tender documentation, and construction supervision.
The works involved excavation and lining of a 1400m canal, construction of powerhouse and intake, construction of spillway, wing walls, highway bridge, installation of steelwork, cranes and gate guides, diversion of a highway, pipes for water and sewerage and telephone cables, relocation of a Police Station, primary school, construction of permanent staff housing and construction of 12Km of approach & estate roads.
Client: Uganda Electricity Board.
Funded by: IDA
Completion Date: 2002
We provide consultancy services for feasibility studies, design, and construction supervision for;
- Hydropower Generation
- Switch Yards
- Sub-Stations
- HV and MV Transmission Lines